A pert activity has the following three time estimates


A PERT Activity has the following three time estimates: Optimistic Time (a)= 12 weeks Pessimistic time (b)= 24 Weeks Most Likely Time (m)= 15 The expected completion time (te+/- SD) for this activity is: a. 17+/-4 b. 16+/-4 c. 18+/-2 d. 16+/-2 Weeks

Request for Solution File

Ask an Expert for Answer!!
Operation Management: A pert activity has the following three time estimates