A project was planned using pert with three time estimates


A project was planned using PERT with three time estimates. Times expected completion times of the project was determined to be 36 weeks. The variance of critical path is 25

A) What is the probability that the project will be finished in 32 weeks or less?

B) What is the probability that the project takes longer than 36 weeks?

C) What is the probability that the project will be finished in 42 weeks?

D) What is the probability that the project will take longer than 45 weeks?

E) The project manager wishes to set the due date for the completion of the project so that there is a 90% chance of finishing on schedule. Thus, there would only be a 10% chance the project would take longer than this due date what should this due date be?