A product has the following requirement the setup cost each


A product has the following requirement. The setup cost each time is $150, the inventory holding cost is $2.50 unit per week. There is no Begging Inventory, and there is no scheduled receipts. Assume the lead time is 0.

1. Determine the MRP using the EOQ lot-sizing rule.

Find the EOQ from the information giving in Excel 


Attachment:- Blackberry Final Report.docx

Solution Preview :

Prepared by a verified Expert
Operation Management: A product has the following requirement the setup cost each
Reference No:- TGS01208887

Now Priced at $20 (50% Discount)

Recommended (95%)