A job was timed for 60 cycles and had an average of 12


A job was timed for 60 cycles and had an average of 1.2 minutes per piece. The performance rating was 93 percent, and workday allowances are 19 percent. Determine each of the following:

Observed Time _____ minutes

Normal Time ____ minutes

Standard time ____ minutes