A job shop received an order for high-precision formed


A job shop received an order for high-precision formed parts The following data is given: Revenue: $135,000 per each good part Cost Salvage$0.00 Probability of good part: 0.75 (Binomial Distribution) S55,000 per each part Customer requires at least 8 and not more than 10. If fewer than 8 are produced, the customer will not purchase any. Also, the customer will not purchase over 10 parts. What is my maximum expected profit?