A firm has an asset beta of 1 and a company cost of capital


Please have the formula's as part of your answers.

A firm has an asset beta of 1 and a company cost of capital of 15%. A new project comes along with a beta of .2 and an expected return (IRR) of 10%. Putting the project’s beta into the CAPM gives the project a return of 5% based on project risk. Should the firm accept or reject the project? Explain.