A fabrication cell at spradelys rockets uses the pull


A fabrication cell at Spradelys Rockets uses the pull method to supply gears to an assembly line, which requires 339 gears per day. Containers typically wait 0.8 day in the fabrication cell. Each container holds 64 gears and one container requires 1.4 day in machine time. Set up times are negligible. If the policy variable for unforeseen contingencies is set at 0.02, how many containers should Jitson authorize for the gear replenishment system? Jitson should authorize__________containers.