A company is in the business of machining parts that go


Question: A company is in the business of machining parts that go through various work centers. Suppose work center A feeds work center B with parts. The following times (in minutes) are given for each work center.

1963_WC.png

transferred from work center A to work center B. The demand rate at work center B is four parts per minute.

a. How many kanban containers are needed for this situation?

b. If move time is cut in half, what does this do to the number of containers needed? How much will this change reduce inventory?

Request for Solution File

Ask an Expert for Answer!!
Operation Management: A company is in the business of machining parts that go
Reference No:- TGS02707254

Expected delivery within 24 Hours