A batch production operation has a machine setup time of 30


A batch production operation has a machine setup time of 3.0 hours and a processing time of 1.60 min per cycle. Two parts are produced each cycle. No tool handling time is included in the cycle. Part handling time each cycle is 45 sec. It consists of the worker obtaining two starting work units from a parts tray, loading them into the machine, and then after processing, unloading the completed units and placing them into the same tray. Each tray holds 24 work units. When all of the starting work units have been replaced with completed units, the tray of completed parts is moved aside and a new tray of starting parts is moved into position at the machine. This irregular work element takes 3.0 min. Batch quantity is 2400 units.

Determine following:

(a) Average cycle time?

(b) Time to complete batch?

(c) Average Production rate?

Request for Solution File

Ask an Expert for Answer!!
Operation Management: A batch production operation has a machine setup time of 30
Reference No:- TGS01140413

Expected delivery within 24 Hours