8 batch of material visits 5 workstations in sequence to be


8. Batch of material visits 5 workstations in sequence to be converted to finished product Each batch has 100 units. The setup time at each workstation is l hour. The processing time is 1.2 minutes per unit. The material- handling time from one machine to the next via a fork-lift truck is 1 hour. Find the lead time of the batch.

Request for Solution File

Ask an Expert for Answer!!
Operation Management: 8 batch of material visits 5 workstations in sequence to be
Reference No:- TGS02235076