If you order these jobs by shortest process time rule the


You have the following information on four jobs. Today is the beginning of day 1, so you can assume that the Time needed = work remaining and Due (days) = time remaining.

Job

Time Needed (days)

Due (days)

R

3

7

S

2

4

T

4

15

U

5

9

If you order these jobs by Shortest Process Time rule, the order will be: [ Select ]

If you order these jobs by Earliest Due Date rule, the order will be: [ Select ]

What is the Average Flow Time if the jobs are scheduled using the Shortest Processing Time rule: [ Select ]