Draw the line balance in order to minimize the number of


A production line with 12 tasks has the precedence relationships and durations presented in the following table. The line runs 8 hours a day and has a daily demand of 80 products, but a demand reduction is anticipated that will reduce demand to half its current level.

Task

Precedence

Duration(min)

A

-

6

B

-

9

C

A

4

D

A

5

E

B

4

F

C

2

G

C,D

3

H

F

7

I

G

3

J

E,I

1

K

H,J

10

L

K

1

1. Draw the line balance in order to minimize the number of workstations according to the largest-positional-weight heuristic

2. Determine the total idle time, the lead time, and the work-in process.

3. Make a sketch of the cell layout indicating what tasks will be carried out in each station by the assigned workers.

Request for Solution File

Ask an Expert for Answer!!
Operation Management: Draw the line balance in order to minimize the number of
Reference No:- TGS02717570

Expected delivery within 24 Hours