Your project is halfway complete and your boss wants more


Your project is halfway complete and your boss wants more data to ensure the project will complete on schedule. You have been tracking EV, SPI and CPI and feel confident the project is on schedule. Your boss's gut feeling disagrees and wants more data using other methods. How would you demonstrate your KPI's are on target?