Your government program team is developing a new underwater


Your government program team is developing a new underwater helmet equipped with enhanced visualization technology. Condensation issues threaten the visibility of the screen and your team does not have the means to deal with the risk. You contract with a separate group of industry materials and mechanical engineers since they can better address that specific risk and offer a set of solutions back to you as you monitor their progress.

This is an example of which mitigation strategy?

1. Acceptance

2. Avoidance

3. Transfer

4. Control