Your firm is considering a project with the following


Your firm is considering a project with the following timeline and cash flows:

Year 0: -$3,000     Year 1: $850     Year 2: $980     Year 3: $1,010     Year 4: $1,200     Year 5: $1,450

If the appropriate cost of capital is 9 percent, what's the NPV statistic for the project, and should the firm accept or reject the project with the cash flows given?

A. -$1284.19; Reject     B. -$1124.45; Accept     C. $1,326.24; Reject     D. $1,177.08; Accept