Your company completed the east side subdivision the costs


Question: Your company completed the East Side subdivision. The costs are shown in Figure. The site concrete labor and outside lighting were done by subcontractors. The grading and excavation, sanitary sewer, water line, and storm drain were done by the company's excavation crew. The company's minimum profit and overhead markup is 15%. Determine the profit generated by the estimator, project management, and the excavation crew on this project.

1656_11-4.png

Request for Solution File

Ask an Expert for Answer!!
Accounting Basics: Your company completed the east side subdivision the costs