Your company can accept one of three possible projects


Your company can accept one of three possible projects. Project A has a net present value (NPV) of US $30,000 and will take six years to complete. Project B has an NPV of US $60,000 and will take three years to complete. Project C has an NPV of US $90,000 and will take four years to complete. Based on this information, which project should the company choose?

A. They all have the same value.

B. Project A

C. Project B

D. Project C