Your acquisition program expects to award a vehicle


Your acquisition program expects to award a vehicle production contract in April 2017. The first item from this contract is expected to be delivered in January 2019. The estimated unit cost for each vehicle is $11 million (then-year dollars) and the contractor can deliver exactly 3 items per month beginning in January 2019. No advance procurement will be used for this contract. What is the maximum amount that may be budgeted for the FY 2017 vehicle production contract that still complies with applicable DoD funding policies?

Solution Preview :

Prepared by a verified Expert
Business Management: Your acquisition program expects to award a vehicle
Reference No:- TGS02742819