You overhear two project members arguing about the project plan. One member advocates doing the riskiest work first in a time box and when the time runs out, build on what has been produced successfully and do what remains in Pareto order. The other argues that the work must be done starting with what the client needs the most and work in customer priority order. What is your opinion, and how would you explain your rationale to these two serious members of your team?