You have just determined the actual number of workstations


Question: You have just determined the actual number of workstations that will be used on an assembly line to be 25 using the assembly-line balancing procedure. The cycle time of the line is 30 seconds and the sum of all that tasks required on the line is 10 minutes. What is the line's efficiency?