You have been hired as a project management consultant to


You have been hired as a project management consultant to assist the Acme Company in evaluating two different project proposals they are considering. Proposal A calls for the construction of a new plant which will require three years to complete and will have much greater capacity than the old plant. Because the plant will have to be built on the current site, the old plant will have to be razed. Proposal B involves the renovation of this plant. This renovation will require two years to complete, but the plant can remain in operation in a reduced capacity during this upgrade. Once the renovation is complete revenue will be increased by 25% per year, however annual maintenance will be 50% higher than Proposal A.

Proposal B: Renovate Existing Plant                 

                  Year1      Year2     Year3      Year4      Year5      Year6      Year7     Year8      Year9      Year10

Revenue      100         100         350         350           350          350         350          350         350           350

Expense      500          500          75            75           75            75           75            75            75             75

a. What is the profit associated with the project carried out in Proposal A? Proposal B?

b. When does payback occur on the project carried out in Proposal A? Proposal B?

c. What is the present value of revenue for the project carried out in Proposal A? Proposal B? (In computing present value, do not discount the value for the first year being examined.) (Assume i = 0.10)

d. What is the present value of expense for the project carried out in Proposal A? Proposal B? (In computing present value, do not discount the value for the first year being examined.) (Assume i = 0.10)

e. What is net present value for the project described in Proposal A? Proposal B? (In computing present value, do not discount the value for the first year being examined.) (Assume i = 0.10)

f. What is the internal rate of return for the project described in Proposal A? Proposal B?

g. Which project would you recommend? Why? What are the merits? What are the risks