you are working on a project that has 12


You are working on a project that has 12 activities. You determine that the critical path consists of only five activities. You then compute the variances for the five critical path activities and these variances are 3, 4, 2, 1, and 6 days. The desired completion date for the project is 44 days and the expected completion date for the project is 40 days. Which of the following alternatives gives the probability that the project will be completed by the desired completion date?

Request for Solution File

Ask an Expert for Answer!!
Operation Management: you are working on a project that has 12
Reference No:- TGS0402405

Expected delivery within 24 Hours