You are the project manager of a new aerospace project


You are the project manager of a new aerospace project named Project Orion. You have been given the following budget baseline:

Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7

$10M $25M $40M $35M $15M $5M $1M

The cash flow available for Project Orion is:

Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7

$10M $15M $10M $50M $15M $30M $21M

Assume that inflation is zero and that there is no need to discount the values. Answer the following questions:

1. What is the cash flow shortfall by year and cumulatively?

2. What options would allow the project to proceed?

3. What are all the possible sources of funding for this project?

Minimum of three pages in a Word document