You are the project manager of a large virtual financial


You are the project manager of a large, virtual financial project. You want to improve the functioning of the project team. Which of the techniques below would not likely improve the effectiveness and efficiency of the project team?

A. Establish a code of conduct for the project team.

B. Create a process to handle conflict.

C. Ensure all members of the team fully understand the project scope.

D. Hold face-to-face meetings whenever possible.

Request for Solution File

Ask an Expert for Answer!!
Operation Management: You are the project manager of a large virtual financial
Reference No:- TGS01122157

Expected delivery within 24 Hours