You are managing a vendor using a cpif contract the target


You are managing a vendor using a CPIF contract. The target contract PRICE was negotiated for $635K with a $35K fee for the vendor. The share ratio for any underrun is 80/20, for an overrun it is 60/40. The vendor completes the work at an actual cost of $625K. What is the final fee the vendor will receive?