You are given the following information about a


1) You are given the following information about a dry-batchpaving operation. You are going to use one mixer that has a servicerate of 30 serives/hr. The dry-batch trucks you use forbringing concrete to the paver have an arrival rate of 7.5 arrivals/hr. Each truck carries 6 cu yd of concrete. You have a totalamount of 13,500 cu yd of concrete to pour. You rent a truckat $100/hr, and the paver at $300/hr.If the job takes more than 80hrs, you pay a penalty of $700/hr owing to delays in jobcompletion. On the basis of least cost, determine the numberof trucks you should use. Plot the cost versus the number oftrucks used.

2) As a contractor, you are blasting rock out of a quarry andhauling it down to the waterfront in dump trucks to form a jetty(see picture on following page).

Quarry blasting

Blasted rock has 0.69 swell factor

Loose rock density = 1.4 tons/yd3

Blasting produces 500 yd3 of loose rock every houron average

Efficiency is already factored in to the blasting productionrate

Trucking

You have 5 off-road dump trucks to transport the rock

Capacity = 25 yd3 of loose rock each on average

Efficiency: trucks work 55 minutes out of every hour

Typical haul cycle:

5 minutes loading

8 minutes from quarry to jetty

1 minute dump

8 minutes return trip

Jetty placement

The jetty consists of 100,000 yd3 of rock materialthat you must place

Once placed, “jetty rock” has an average density of1.45 tons/yd3 in place

It takes 3 minutes for the excavator on the jetty to adjust therocks dumped by each truck so that they are properly positioned inthe jetty. The next truck cannot dump its rocks until the excavatoris done with the positioning from the previous truck.

Efficiency: excavator works 50 minutes out of every hour

Answer the following questions:

What is the density of the rock (in tons/yd3) in the bank before it is blasted out?

How many complete cycles can a truck make in 1 hour?

What is the productivity of this operation in terms ofyd3/hr of jetty rock?

How many total truck loads do you need to place all the jettyrock?

Request for Solution File

Ask an Expert for Answer!!
Civil Engineering: You are given the following information about a
Reference No:- TGS0799057

Expected delivery within 24 Hours