You are forecasting your estimate to complete your project


You are forecasting your estimate to complete your project and are incurring extra costs to do this work. What sort of estimating techniques are you using?

A. Bottom-up EAC estimating

B. Earned value management

C. Estimate to complete forecast

D. To complete performance index