You are creating a customer database for the modesto nuts


You are creating a customer database for the Modesto Nuts minor league baseball team. Draw a project network given the information below. Complete the forward and backward pass, compute activity slack, and identify the critical path.

How long will this project take? How sensitive is the network schedule? Calculate the free slack and total slack for all noncritical activities.




Time

ID

Description

Predecessor

(days)

A

Systems design

None

2

B

Subsystem A design

A

1

C

Subsystem B design

A

1

D

Subsystem C design

A

1

E

Program A

B

2

F

Program B

C

2

G

Program C

D

2

H

Subsystem A test

E

1

I

Subsystem B test

F

1

J

Subsystem C test

G

1

K

Integration

H, I, J

2

L

Integration test

K

1

Solution Preview :

Prepared by a verified Expert
Management Theories: You are creating a customer database for the modesto nuts
Reference No:- TGS0652877

Now Priced at $20 (50% Discount)

Recommended (95%)

Rated (4.7/5)