Use the appropriate formulas for
Total Time
Capacity
Utilization
You are considering the purchase of a new machine to help produce a new product line being introduced. The machine is expected to have a setup time of 20 minutes per batch and a processing time of 1.5 minutes per part. You plan to have batch sizes of 60 parts. The plant operates 8 hours per day.
Draw a Gantt Chart for the process.
i. Show the Cycle times
ii. MTT
What is the capacity of the machine in batches per day?
What is the capacity of the machine in parts per day?
How many batches per day can you run through the machine if you plan to operate the machine at a 75% utilization rate?
How many parts per day can you process through the machine if you plan to operate the machine at an 80% utilization rate?