You are considering project b that requires an initial


You are considering Project B that requires an initial investment of $70. The current present value of its cash flows is estimated to be $100 based on today’s market conditions. You can undertake Project B now or wait for one month to decide. The current risk-free rate is 0.25%, and the standard deviation of project return is 10%. What should you do?