You are a project manager of a construction project during


You are a project manager of a construction project; during the weekly meeting with the owner and designer; you asked the designer whether you can use wood forms for pouring the concrete foundation instead of steel forms that the project specifications call for. The designer accepted this idea.

What should you do in this case to confirm and document the above? (Use the best documentation practices)