You are a production planner for stanley tools stanley


You are a production planner for Stanley Tools. Stanley Tools faces an annual demand of 1,000 screws. Production rate is 8 screws per day. Production setup cost is $10 per setup and annual holding cost is $2 per screw. Stanley Tools operates 250 days in a year. (a) What is the optimum production run quantity? (b) What is the maximum inventory level?

Request for Solution File

Ask an Expert for Answer!!
Operation Management: You are a production planner for stanley tools stanley
Reference No:- TGS01294192

Expected delivery within 24 Hours