X company wants to estimate overhead costs in march using


Question - X Company wants to estimate overhead costs in March, when production is expected to be 1,400 units. To determine the parameters of its overhead cost function, it used account analysis with the January cost information below and when production was 1,000 units.

 

Total

Total Variance

Utilities

$43,100

$43,100

Maintenance

70,000

33,600

Supervision

23,000

0

Using the resulting cost function, what is X Company's estimate of total overhead costs in March?

Solution Preview :

Prepared by a verified Expert
Accounting Basics: X company wants to estimate overhead costs in march using
Reference No:- TGS02932682

Now Priced at $20 (50% Discount)

Recommended (90%)

Rated (4.3/5)