Wreck it ralph has been given a contract to demolish just


Wreck It Ralph has been given a contract to demolish (just the wrecking part, not the clean up part) a total of 90,000 square meters of dilapidated government buildings. Here are the parameters of his contract:

  • Budget: $14,600
  • Schedule: 21 days

Wreck It Ralph is now 14 days into the project, and he has successfully demolished 62,000 square meters of buildings and has spent a total of $10,400 of his budget.

What amount of square meters of demolition should have been completed at day 14 per the project plan (round to nearest square meter)?

At day 14, what is remaining budget that should have been available per the project plan (round to nearest dollar)?