Would the project take longer would anything else


Each student should complete the following problem and submit a single file in Word or Excel with all requirements in either format. Given the following information about a small project, Task Duration Immediate Estimates Predecessors A 2 days None B 5 days A C 1 day B D 2 days A E 3 days B & D F 12 days E & C. Using MS Excel, produce a Gantt chart for this project. What would happen if a new estimate for task D increases its expected duration from two days to six days? Would the project take longer? Would anything else change?

Request for Solution File

Ask an Expert for Answer!!
Operation Management: Would the project take longer would anything else
Reference No:- TGS02894307

Expected delivery within 24 Hours