Work content time 420 min assume line efficiency 097


A manual assembly line is being designed for a product with annual demand = 100,000 units. The line will operate 50 wk/yr, 5 shifts/wk, and 7.5 hr/ shift. Work units will be attached to a continuously moving conveyor. Work content time = 42.0 min. Assume line efficiency = 0.97, balancing efficiency = 0.92, and repositioning time = 6 sec. Determine

(a) hourly production rate to meet demand,

(b) number of workers required, and (c) the number of workstations required if the estimated manning level is 1.4.

Request for Solution File

Ask an Expert for Answer!!
Mechanical Engineering: Work content time 420 min assume line efficiency 097
Reference No:- TGS01658182

Expected delivery within 24 Hours