Will firms decision change as the the discount rate changes


Question:

A project that costs $3,000 to install will provide annual cash flows of $800 for each of the next 6 years. Is this project worth pursuing, if the discount rate is 10 percent? How high can the discount rate be before you would reject the project?

PAYBACK A project that costs $2,500 to install will provide annual cash flows of $600 for the next 6 years. The firm accepts projects with payback periods of less than 5 years. Will the project be accepted? Should this project be pursued, if the discount rate is 2 percent? What if the discount rate is 12 percent? Will the firm's decision change as the the discount rate changes?

Solution Preview :

Prepared by a verified Expert
Finance Basics: Will firms decision change as the the discount rate changes
Reference No:- TGS02046521

Now Priced at $20 (50% Discount)

Recommended (99%)

Rated (4.3/5)