Question: Provide responses to the following questions

1. What is the purpose of a staffing management plan? What does it address?

2. Whom should the project manager consult when performing resource leveling?

3. Describe the two primary techniques for compressing a schedule?

4. When crashing a project schedule, describe the two criteria that are considered when considering which activities will be sped up.

Responses should be presented in a question-response format. Use Arial font with 11 point. There is no word limit.