Which type of chart provides the least predictive value


Assignment

Part 1

Question 1
Smoothing out project resources from period to period is called
Resource leveling
Resource allocation or resource limited planning
Better effort planning
Slack utilization planning

Question 2
Which of the following scheduling techniques is most appropriate today for managing a project?
BAR charts
Milestone charts
PERT charts
Precedence charts

Question 3
The major disadvantage of using a bar chart on large projects is that bar charts:

Cannot identify critical paths
Cannot identify milestones
Do not show dependencies between activities

Question 4
Laying out a network diagram when you know before-hand the size of the available resource pool is called:

Resource leveling
Resource allocation or resource limited planning
Better effort planning
Slack utilization planning

Question 5
Activities with zero time durations are called:

Low-slack activities
No-slack activities
Dummy activities
Special activities

Question 6
If the slack in a 12 week activity is 6 weeks and ES = 4, then LF = _____.

4
10
16
22

Question 7
Which of the following schedule compression techniques usually requires adding more resources to each work package that is being compressed?

Overtime
Crashing
Outsourcing
Descoping

Question 8
A charting technique designed to illustrate the inductive and deductive reasoning necessary to achieve some objective is called a _____ Diagram / network

Gantt
Logic
Descriptive
Intuition

Question 9
Which of the following is normally not one of the three critical parameters provided in information reporting to the customer?

Time
Cost
Performance
Risks

Question 10
Which type of chart provides the least "predictive" value?

Bar chart
PERT
ADM
PDM

Question 11
When a functional manager tells you that your project is 10% more difficult than the standard project, the functional manager is providing you with a _____ estimate.

Parametric
Analogy
Engineering
Grassroots

Question 12
Which of the following projects would most likely have reasonably good estimating techniques?

Construction
R & D
Software development
New product development

Question 13
An employee earning $40/hour works in a department where the overhead is 125%. A billable or charge back hour to this department would be:

$ 40
$ 50
$ 90
$ 100

Question 14
Which of the following is generally not part of capital budgeting?

Life cycle cost estimating
Net present value
Internal rate of return
Discounted cash flow

Question 15
Which of the following standard project estimating techniques is usually accomplished in weeks?

Parametric
Analogy
Engineering
Grassroots

Question 16
Material provided in a proposal to justify one's estimates are called:

Supporting pricing
Back-up data
Risk justification
Proprietary pricing

Question 17
Which of the following components of life cycle costing incurs the largest cost?

R & D
Production
Operational and Support
Disposal

Question 18
Pricing out the construction cost of a home by a cost per square foot would be representative of a _____ estimate.

Parametric
Analogy
Engineering
Grassroots

Question 19
The person or group with greatest ability to influence cost at project initiation is:

The customer/owner
The project manager
The project team
The users

Question 20
Variance envelopes are usually established because:

All cost variances must be accounted for and explained
Not all cost variances must be explained even though they exist
All schedule variances must be explained
All cost overruns require sponsor authorization

Question 21
Work that does not lend itself to subdivision into discrete scheduled increments of work, such as project support, is called:

Measurable effort
Level of effort
Discrete estimates
Work package effort

Question 22
A common cause for a favorable CV but unfavorable SV might be:

Too many workers on the project
Too few workers on the project
Crashing the project
Use of overtime

Question 23
The form that is used to establish charge numbers is the:

Responsibility Assignment matrix
Work authorization form
Work package
Cost account change notice

Question 24
If the schedule variance is positive and the cost variance is negative, the project's status is:

Over budget and behind schedule
Over budget and ahead of schedule
Under budget and behind schedule
Under budget and ahead of schedule

Question 25
The best method to price out a work package is to use the:

Average departmental labor rate
Average pay grade labor rate
Actual salary of the workers assuming they are known
Statistical data from the Payroll Department

Part 2

Question 1
Which of the following is normally not one of the three parameters considered during tradeoffs?

Time
Cost
Performance
Financial risks

Question 2
Which of the following generally gets reduced during tradeoffs?

Time
Cost
Performance
Financial risks

Question 3
Assigning high, medium or low to a potential risk is part of:

Risk identification
Quantitative risk assessment
Qualitative risk assessment
Risk response

Question 4
Brainstorming, assumption analysis and WBS decomposition are techniques used for:

Risk identification
Risk assessment
Risk monitoring and control
Risk handling

Question 5
Which of the following is not considered to be an insurable risk?

Direct property damage
Indirect consequential loss
Legal liability
Inflation

Question 6
If a project manager awards a firm-fixed price contract to a supplier, he / she is using:

Acceptance/Assumption
Avoidance
Control/mitigation
Transfer

Question 7
Monte Carlo simulation is a technique used as part of:

Risk identification
Risk assessment
Risk monitoring and control
Risk handling

Question 8
Which risk handling mode is a project manager using if he / she throws out one of three designs for a new product?

Acceptance/Assumption
Avoidance
Control/mitigation
Transfer

Question 9
A technique that uses a series of probability distributions and then transforms them into various risks is called:

Probability estimating
Monte Carlo simulation
Estimating simulation
Black box analysis

Question 10
If a project manager believes in a proactive rather than reactive risk management approach, he/she is using:

Acceptance/Assumption
Avoidance
Control/mitigation
Transfer

Question 11
An intentional relinquishment of a legal right is a (n):

Infringement
Breach of contract
Waiver
Termination liability

Question 12
The type of contract where all of the seller's costs are reimbursed and the seller will also receive a percentage of the profit pool based upon how well the buyer likes the end result is a _____ contract.

Cost-sharing
Cost-plus-award-fee
Cost-plus-fixed-fee
Cost-plus-incentive-fee

Question 13
"Hygiene Factors" refers to:

How a contractor should respond to an RFP
The type of proposal expected by the seller
How and where contract negotiations will take place
How many bidder conferences will be held

Question 14
Which of the following is generally not included in a solicitation package?

Listing of qualified vendors
Past bidding history of qualified vendors
How changes will be managed
Supplier payment plan

Question 14
Which of the following is generally not included in a solicitation package?

Listing of qualified vendors
Past bidding history of qualified vendors
How changes will be managed
Supplier payment plan

Question 15
During contract negotiations, the goal of the buyer is to:

Get the seller to accept the greatest risk
Get the highest quality result for the lowest price
Get the seller to agree to scope changes at no cost to the buyer
Try to get the least amount of work done at the lowest price

Question 16
Which type of cost-plus contract provides the seller with a guaranteed dollar-value profit rather than as a percentage?

Cost-sharing
Cost-plus-award-fee
Cost-plus-fixed-fee
Cost-plus-incentive-fee

Question 17
Billing the cost of repairs against a financially closed out project is called _____.

Back charging
Refinancing
Order of precedence
Arbitration

Question 18
Which of the following is generally not part of "Conducting the Procurements"?

Perform a make-or-buy analysis
Confirm qualified sources
Review past performance of sources
Produce a solicitation package

Question 19
Acceptance sampling is a statistical process for evaluating a portion of lot for the purpose of:

Measuring the weight of each sample
Measuring the length and width of each sample
Measuring the volume of each sample
Acceptance or rejection of the entire lot

Question 20
The cause and effect chart is used to _____.

Identify a problem
Determine its cause
Prioritize a solution
Decide upon a course of action

Question 21
Design of experiments is attributed to:

Deming
Juran
Crosby
Taguchi

Question 22
Which of the following is not one of the four categories of the cost of quality?

Prevention
Identification
Internal failures
External failures

Question 23
The collective term for the activities and techniques within the overall process is called:

Quality control
Quality assurance
Quality policies
Quality visions

Question 24
The balance between quality and cost is called:

Salability
Produceability
Operability
Availability

Question 25
The fact that random variation is always present in any process is called:

Common cause variability
Special cause variability
Assignable cause variability
Control limit variability.

Solution Preview :

Prepared by a verified Expert
Business Management: Which type of chart provides the least predictive value
Reference No:- TGS02342813

Now Priced at $50 (50% Discount)

Recommended (91%)

Rated (4.3/5)