2. An activity on a PERT network has an optimistic time of 3 weeks, a most likely time of 6 weeks, and a pessimistic time of 18 weeks. Find its Standard Deviation.

a. 2 weeks

b. 0.5 weeks

c. 2.5 weeks

d. 1.5 weeks

e. 1 week