Which one of the following increases the net present value


Which one of the following increases the net present value of a project?

A. an increase in the required rate of return

B. an increase in the initial capital requirement

C. a deferment of some cash inflows until a later year

D. an increase in the aftertax salvage value of the fixed assets

E. a reduction in the final cash inflow