Which one of the following costs was incurred in the past


1. A project will produce an operating cash flow of $31,200 a year for 7 years. The initial fixed asset investment in the project will be $204,900. The net aftertax salvage value is estimated at $62,000 and will be received during the last year of the project's life. What is the net present value of the project if the required rate of return is 11 percent?

A. -$22,627.54

B. -$28,016.66

C. $4,120.52

D. $21,040.83

2. Which one of the following costs was incurred in the past and cannot be recouped?

Incremental

Side

Sunk

Opportunity

Request for Solution File

Ask an Expert for Answer!!
Financial Management: Which one of the following costs was incurred in the past
Reference No:- TGS02148495

Expected delivery within 24 Hours