Which of the periods have planned order releases of x what


Use the following bill of material information for all of the MRP problems that follow. Each X is made up of one Y and 2 Zs. Each Y is made up of 2 As and one B. Each Z is made up of 3 As and 1 C. Use the following info for the MRP Problems that follow regarding X. Gross Requirements for periods 1-8 are: 700, 500, 800, 700, 900, 1,100, 500, & 600. The inventory info follows:

Lot Size: 1,000

On Hand: 1,300

Safety Stock: 300

Allocated: 0

Lead time: 1

Which of the periods have planned order releases of x?

What is the projected on hand at the beginning of period 1 for x?

What is the projected on hand at the beginning of period 8 for x?

What is the planned order release for X for periods 1-8? (Can be zero)