Which of the following times for the fourth unit would be


1. Suppose the first unit required 800 hours and the second unit required only 680. Which of the following times for the fourth unit would be consistent with a true learning curve scenario?

2. A job is expected to have a learning curve of 90 percent. The third unit required 16 hours. The 12 th unit should take approximately how many hours?