Which of the following statements regarding critical paths


Which of the following statements regarding critical paths is true?

A-The shortest of all paths through the network is the critical path

B-Some activates on the critical path may have slack

C-Every network has only one critical path

D- On a specific project, there can be multiple critical paths, all the exactly the same duration.

E- The duration of the critical path is the average duration of all paths in the project network

Request for Solution File

Ask an Expert for Answer!!
Operation Management: Which of the following statements regarding critical paths
Reference No:- TGS01121168

Expected delivery within 24 Hours