Which of the following statements is true regarding


Which of the following statements is TRUE regarding critical paths?

The path that takes the shortest time to complete in a project is the critical path.

Some activities on the critical path may have positive slack time.

Some non-critical activities may have zero slack time.

For any project, the (expected) project completion time is equal to the (expected) time duration of the project’s critical path.