Which of the following statements describles the lf time


1. Which of the following statements describles the LF time for an activity in a project?

A. The smallest LS time of all its immediate predecessors

B. The largest EF time of all its immediate predecessors

C. The smallest LS time of all its immediate predecessors

D. The LS time of the activity minus the activity duration

E. The ES time of the activity plus the activity duration

2. If a supply chain is designed to be responsive, which of the following scenarios is most likely to be true?

A. Demand is predicatble

B. Product variety is low

C. Suppliers offer low cost

D. Suppliers have volume flexibility

E. Contribution margins are low

Request for Solution File

Ask an Expert for Answer!!
Operation Management: Which of the following statements describles the lf time
Reference No:- TGS02911577

Expected delivery within 24 Hours