Which of the following statements about the qualitative approach to project risk assessment is most correct?

Qualitative risk assessment involves the answers to a series of yes/no questions.

Typically, “yes” answers are assigned one point and “no” answers zero points.

The higher the score, the greater the risk.

Typically, qualitative risk assessment is used in conjunction with a quantitative risk assessment (as opposed to replacing a quantitative risk assessment).

All of the above statements are correct.