which of the following items best depicts the


Which of the following items best depicts the Define Scope process?
A. It begins by determining product scope / deliverables and culminates in a project scope statement.
B. It begins by estabilishing a scope baseline and culminates in a product specification.
C. It beging with user requirements and culminates in a product specification.
D. It beging with a business case and culminates in a project charter.