Which of the following is the correct formula to calculate


1. Which of the following is the correct formula to calculate the projected available balance?

A) Projected Available Balance = Beginning Balance + Master Produciton Schedule - Forecast

B) Projected Available Balance = Beginning Balance - Master Produciton Schedule + Forecast

C) Projected Available Balance = Beginning Balance + Master Produciton Schedule + Available to Promise

D) Projected Available Balance = Beginning Balance + Master Produciton Schedule + Forecast

2. Which of the following is used to show the components that make up a product as well as the quantity of each component required?

A) Final Assembly Schedule

B) Bill of Materials

C) MPS Record

D) MRP Record

Request for Solution File

Ask an Expert for Answer!!
Operation Management: Which of the following is the correct formula to calculate
Reference No:- TGS02261312

Expected delivery within 24 Hours